Board of Public Works

Wednesday, April 8, 2026 · Government meeting record

The 30-second read

Recorded outcome

The Board of Public Works will meet on April 8, 2026, to review infrastructure projects, including street acceptances, bid awards for road and safety improvements, and various contract adjustments.

Why it matters

This meeting determines the approval of over $5.5 million in city infrastructure spending and the formal acceptance of new residential streets.

What happens next

No later meeting or follow-up date is stated in the reviewed record.

An official outcome record - an action agenda or minutes - is published for this meeting.

Record text

No recording or transcript is held for this meeting.

Board of Public Works - Meeting Minutes

April 8,2026

Location: Public Assembly Room - City County Building

Chair Todd Wilson called the meeting to order at 1:00 p.m.

Board Members: Susie Cordi, Daniel Haake, and Leslie Schulte.

Board Counsel: Benjamin Morrical

Staff Present: Jasmine Dillard, Nathan Sheets, Mark St. John, and Margaret Wilson.

This meeting can be viewed on Government Access Television Channel 16.

Chair Todd Wilson called for a motion to adopt the agenda for April 8,2026.

Leslie Schulte moved to adopt the agenda. Susie Cordi seconded. The motion was approved 4-0.

a. Hickory Run, Section 1

Staff recommended that the Board of Public Works approve and authorize the acceptance of 0.51 miles of streets associated with the Hickory Run, Section 1 subdivision, following receipt of as-built documents and Certificates of Completion and Compliance.

Daniel Haake moved to approve the street acceptance. Leslie Schulte seconded. The motion was approved 4-0.

b. Sagebrook West, Section 2

Staff recommended that the Board of Public Works approve and authorize the acceptance of 0.41 miles of streets associated with the Sagebrook West, Section 2 subdivision, following receipt of as-built documents and Certificates of Completion and Compliance.

Susie Cordi moved to approve the street acceptance. Daniel Haake seconded. The motion was approved 4-0.

Leslie Schulte inquired how the intersections were selected. Nathan Sheets responded that the intersections were identified based on high crash data, noting they have consistently appeared on the list over time due to the number of reported incidents. He explained that while crash data is a key factor in engineering decisions, the proposed installation of video detection will allow for additional analysis, including near-miss events.

Substantial Completion is scheduled for August 31,2026,with Final Completion scheduled for December 31,2026. The Engineer's Estimate for construction was $673,000.00.

a. Video Detection at Crash-Sensitive Intersections

* * *

This approach provides a more proactive assessment, as the difference between a near miss and a crash can be a matter of seconds or a few feet. Sheets added that the project also includes video detection along Allisonville Road from Binford Boulevard to 86th Street.

He noted that many of these intersections currently lack vehicular detection and operate on preset signal timing. With the implementation of video detection, signal timing can be adjusted based on real-time traffic volumes, which is expected to improve traffic flow and reduce congestion. He further noted that reducing congestion may help limit unsafe driving behaviors associated with extended wait times at signals.

Leslie Schulte moved to approve the bid award. Susie Cordi seconded. The motion was approved 4-0.

b. Madison Avenue Rehabilitation - Martin St to Hanna Ave (STBG FY2026)

Staff recommended that the Board of Public Works approve and authorize the Director to award ST-39-059, Madison Avenue Rehabilitation - Martin St to Hanna Ave (STBG FY2026), to Calumet Civil Contractors, Inc., in the not-to-exceed amount of $4,142,000.00 on the basis that they are the lowest responsive and responsible bidder.

Substantial Completion is scheduled for June 25, 2027, with Final Completion scheduled for August 27, 2027. The Engineer's Estimate for construction was $5,208,963.06.

Daniel Haake asked how the department evaluates compliance with its Vision Zero and Complete Streets policies using this project as an example. Nathan Sheets responded that the department utilizes a Complete Streets checklist to review each project. He noted that this effort is part of a larger, multi-phase project funded in three segments. The phase currently under construction represents the northern portion, while this phase corresponds to the southern segment, with a third phase planned between them.

Sheets explained that the project reexamines existing roadway space to improve safety and efficiency. As part of the improvements, the corridor is being reduced from three lanes in each direction to two, which is expected to promote traffic calming by reducing excess roadway capacity that can contribute to speeding. He added that additional safety improvements include pavement resurfacing, new pavement markings, and upgraded intersection equipment. He noted that much of the existing infrastructure is nearing the end of its useful life, with the last major rehabilitation occurring approximately 15 to 20 years ago.

Daniel Haake moved to approve the bid award. Leslie Schulte seconded. The motion was approved 4-0.

a. C/O No. 1: Grassy Creek Greenway - Phase 1

Change Order No.1 provides for compensation and quantity adjustments, including geogrid, additional pipe, and fill for sidewalk, transformer installation, and fence removal, adding 65 days to completion.

Staff recommended that the Board of Public Works approve and authorize the Director to ratify and execute Change Order No.2 to SD-22-101(D), 2022 Thoroughfare Drainage Improvements - Area 2 with E&B Paving, Inc., with no change to the total not-to-exceed amount of $5,099,303.46,and 228 days added to the Substantial and Final Completion dates.

b. C/O No. 2: 2022 Thoroughfare Drainage Improvements - Area 2

Susie Cordi moved to approve the change order. Leslie Schulte seconded. The motion was approved 4-0.

* * *

c. C/O No. 1: Residential Street Reconstruction - Sector 3 (SE)

Staff recommended that the Board of Public Works approve and authorize the Director to execute Change Order No.1 to ST-24-079, Residential Street Reconstruction - Sector 3 (SE) with Howard Asphalt LLC, in the increased amount of $137,749.07, for a total not-to-exceed amount of $3,338,212.72,with no additional days added to the Substantial and Final Completion dates.

Change Order No.1 provides for compensation and quantity adjustments, including underdrain installation at 11th Street and Lick Creek Avenue, and replacement of cold in-place recycling with mill and overlay.

Daniel Haake moved to approve the change order. Leslie Schulte seconded. The motion was approved 4-0.

a. C/O No.1 (Final) and Final Acceptance: Mendenhall Road over Goose Creek (4306L)

Board of Public Works Agenda Date: April 8, 2026 Time: 1:00 PM Location: Public Assembly Room, City-County Building 1. ADOPT THE AGENDA a. Adoption of the April 8, 2026, Agenda 2. STREET ACCEPTANCES Jasmine a. Hickory Run, Section 1 Dillard Jasmine b. Sagebrook West, Section 2 Dillard 3. BID AWARDS Nathan a. Video Detection at Crash Sensitive Intersections Sheets $658,500.00 TC Electric, Inc. TS-25-019 Nathan b. Madison Avenue Rehabilitation – Martin St to Hanna Ave (STBG FY2026) Sheets $4,142,000.00 Calumet Civil Contractors, Inc. ST-39-059 4. CHANGE ORDERS Nathan a. C/O No. 1: Grassy Creek Greenway – Phase 1 Sheets $0.00 Calumet Civil Contractors, Inc. GT-21-001 Nathan b. C/O No. 2: 2022 Thoroughfare Drainage Improvements – Area 2 Sheets $0.00 E&B Paving, Inc. SD-22-101(D) Nathan c. C/O No. 1: Residential Street Reconstruction – Sector 3 (SE) Sheets $137,749.07 Howard Asphalt LLC ST-24-079 5. CHANGE ORDERS – FINAL Nathan a. C/O No. 1 (Final) and FA: Mendenhall Road over Goose Creek (4306L) Sheets ($8,901.07) Olco, Inc. BR-43-001 6. PROFESSIONAL SERVICES AGREEMENTS Mark a. Vandalia Trail St. John $260,130.00 Infrastructure Engineering of Indiana, LLC GT-25-004 7. PROFESSIONAL SERVICES AMENDMENTS Nathan a. Amendment No. 1: Madison Avenue Road Diet – Pleasant Run to Ray Street Sheets $480,620.86 Lochmueller Group, Inc. ST-32-128

8. OTHER BUSINESS None 9. MOTION TO ADJOURN Accessibility Notice For disability-related accommodations, please contact us at 317-327-4000 at least 48 hours in advance.

Official record

ArtifactSourceState
Agenda packetNot published in the sources we holdunavailable
BudgetNot published in the sources we holdunavailable
Action agendaNot published in the sources we holdunavailable
Transcript or captionsNot published in the sources we holdunavailable
AttachmentNot published in the sources we holdunavailable

Coverage and corrections

Records considered

  • Board of Public Works — Minutes
  • Board of Public Works

Not claimed by this page

  • Verified meeting decisions with item-specific public-source evidence
  • Item-level plain-language summaries are not available; this page does not infer individual agenda items.
  • Item-linked, attributed deliberation
  • A source-grounded next meeting date
  • Official outcomes have not been published.
  • A transcript is not available.
  • No audio or video recording is linked.
  • Speakers have not been reliably matched to public profiles.
  • Named people and places have not been reliably resolved.
  • An individual roll-call roster is not available.

No source correction or revision history is recorded for this meeting. A corrected artifact will appear here as a new version rather than replacing what is shown above.