City Commission Work Session Meeting (2025-09-23)

Tuesday, September 23, 2025 · Government meeting record

The 30-second read

Recorded outcome

FEMA First Appeal Response - Repair & Replacement of the Ross Point Pier

The Holly Hill City Commission discussed potential repair and replacement plans for the Ross Point Pier after FEMA denied the city's appeal for storm-damage funding. Officials are now exploring alternative funding sources, such as ECHO grants, and plan to seek bids for initial deck and roof removal.

Why it matters

Holly Hill taxpayers face potential costs ranging from $1.13 million to $1.7 million for pier repairs following the loss of federal disaster funding.

What happens next

No later meeting or follow-up date is stated in the reviewed record.

An official outcome record - an action agenda or minutes - is published for this meeting.

Captured actions

1

Recorded outcomes

1

Source artifacts

1

What changed

Other key decisions

1 captured item has a publicly linked outcome.

Search all 1 meeting actions

People and votes

Debra Snow

Present at this meeting

The reviewed record lists this person as present but does not attribute a motion, statement, or individual vote to them.

Record text

No recording or transcript is held for this meeting.

CITY OF HOLLY HILL, FLORIDA CITY COMMISSION MINUTES ● SEPTEMBER 23, 2025 Large Conference Room Work Session 5:00 PM CITY HALL 1065 RIDGEWOOD AVENUE HOLLY HILL, FL 32117 City Clerk’s office: (386) 248-9441 - Fax: (386) 248-9448 City of Holly Hill, Florida Printed: 9/30/2025 9:36 AM Page 1 1. CALL TO ORDER 2. ROLL CALL Attendee Name Title Status Arrived John Penny Mayor Present Debra Snow City Commissioner Present Penny Currie City Commissioner Present Jeffrey DeLanoy City Commissioner Present Roy Johnson City Commissioner Present 3. FEMA FIRST APPEAL RESPONSE - REPAIR OR REPLACEMENT OF ROSS POINT PIER 1. FEMA First Appeal Response - Repair & Replacement of the Ross Point Pier (Requested by Valerie Manning, City Clerk) Steve Juengst, Deputy Public Works Director mentioned that FEMA has denied the city’s appeal for eligibility to have the Ross Point Pier covered as storm related damage. (A copy of this workshop in its entirety is available on CD upon request in the City Clerk’s Office or available online on the city’s YouTube channel). Mr. Juengst went over a recap of anticipated costs should the city opt to take on the repair/replacement of the Ross Point Pier. 6' Embedment of Pilings This estimate is for returning the pier to pre-disaster condition, which calls for 6' embedment of the pilings. This is not recommended. Construction: $1,025,475 Engineering/Design/CEI @ 10%: $102,547.50 Permitting, etc.: $5,000 Total Cost: $1,133,022.50 Full Embedment of Wooden Pilings This estimate is to use the same materials and footprint of the pre-disaster pier, but include pilings that are driven to refusal. It is possible that if we win our appeal with FEMA, we can pay the difference for the upgrade ourselves, but still get reimbursement

Minutes City Commission September 23, 2025 City of Holly Hill, Florida Printed: 9/30/2025 9:36 AM Page 2 for the 6' embedment quote. Construction: $1,092,355 Engineering/Design/CEI @ 10%: $109,235.50 Permitting, etc.: $5,000 Total Cost: $1,206,590.50 Hardening of Pier This option would be to model the Ross Point Pier after the Riverside Park Pier with concrete pilings to refusal, aluminum hardware and composite decking. Construction: $1,677,555.00 Engineering/Design/CEI @ 10%: $167,755.50 Permitting, etc.: $5,000 Total Cost: $1,699,330.50 These options include the replacement of the boardwalk section. Although not destroyed by Hurricane Milton, the boardwalk is ready for replacement. We could reduce the cost by not replacing the boardwalk and/or not having the pier extend so far into the channel. Mr. Juengst stated the engineering/design estimates were provided by me at 10%, but may be less as particularly the last option is a pre-existing/designed structure through Gator Dock. There was consensus from the Mayor and City Commissioners for staff to contact Army Corp Engineers, get bids on the deck and roof removal and then regroup with the Commission to see how it can be funded, possibly through ECHO grants. 4. ADJOURNMENT The workshop adjourned at approximately 5:30 PM.

All meeting actions

Source coverage incomplete

1 meeting items captured. The published sources do not prove this is the complete docket.

Showing 1 of 1

Browse by category1 actions
  • Agenda item 3Other meeting itemsdiscussion_only - Consensus reached to contact Army Corp Engineers and seek bids for deck/roof removal.

    FEMA First Appeal Response - Repair & Replacement of the Ross Point Pier

    Estimates provided for three repair options ranging from $1.13M to $1.7M.

Official record

ArtifactSourceState
AgendaNot published in the sources we holdunavailable
Agenda packetNot published in the sources we holdunavailable
BudgetNot published in the sources we holdunavailable
Action agendaNot published in the sources we holdunavailable
Transcript or captionsNot published in the sources we holdunavailable
AttachmentNot published in the sources we holdunavailable

Coverage and corrections

Records considered

  • City Commission Work Session Meeting (2025-09-23)

Not claimed by this page

  • Item-level plain-language summaries are not available; this page does not infer individual agenda items.
  • Item-linked, attributed deliberation
  • A source-grounded next meeting date
  • A transcript is not available.
  • No audio or video recording is linked.
  • Speakers have not been reliably matched to public profiles.
  • Named people and places have not been reliably resolved.
  • An individual roll-call roster is not available.

No source correction or revision history is recorded for this meeting. A corrected artifact will appear here as a new version rather than replacing what is shown above.

Canonical record: 838fc8e7e0fc2248e9cff890c5e4b87c. This page changes as stronger artifacts are published; it never overwrites an agenda with minutes.

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record