POLISCOPE

The public record

PUNTAGORDA (CHARLOTTE COUNTY) · LOCALHeld · official record pendingPartial coverage

Punta Gorda Isles Canal Advisory Committee

Monday, December 15, 2025 · Government meeting record

The 30-second read

Record incomplete

Punta Gorda Isles Canal Advisory Committee

Why it matters

The official meeting record is available below. Item-level plain-language summaries are not available yet.

What happens next

The scheduled meeting date has passed. Minutes or an action agenda are not published in the records we hold.

This meeting date has passed and no official outcome record has been published yet. Nothing on this page is a decision.

Record text

No recording or transcript is held for this meeting.

Showing the first 60,000 of 69,687 characters. The full document is at the source.

Robert F Knabe, Chair Ronald P Ludvig, Committee Member Harry G Walberg, Committee Member Jake Dye, Committee Member Jeffrey T D'amico, Committee Member CALL TO ORDER Roll Call Pledge of Allegiance Announcements Next Meeting - January 20, 2025 PUBLIC COMMENTS Anyone wishing to address the Punta Gorda Isles Canal Advisory Committee on any subject may do so at the appropriate time during the meeting. Those who choose to speak must state their name for the record. Each person will be allowed to speak up to a maximum of three minutes. 1. APPROVAL OF MINUTES 1.a Approval of Minutes: Punta Gorda Isles Canal Advisory Committee Meeting of October 20, 2025. 2. REPORTS 2.a Finance Report November 2025 2.b Budget Utilization Report November 2025 2.c Seawall Replacement Status Report November 2025. 2.d Permits Authorized by City Staff November 2025. 2.e Punta Gorda Isles Capital Improvement Status Report November 2025. 2.f Master Permit Agreement Status Report November 2025. 3. QUASI-JUDICIAL PUBLIC HEARINGS PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE AGENDA 120 LAISHLEY COURT, PUNTA GORDA, FLORIDA, 33950 DECEMBER 15, 2025, 1:30 PM 1

3.a Special Permit CCSP 01-2025 3.b Special Permit CCSP 02-2025 3.c Special Permit CCSP 03-2025 4. GENERAL BUSINESS STAFF COMMENTS MEMBER COMMENTS ADJOURNMENT If any person decides to appeal any matter considered at this meeting, he or she may need a record of the proceedings, and for such purpose he or she may need to ensure that a verbatim record of the proceedings is made, which record includes the testimony and evidence upon which the appeal is to be based. In accordance with the Americans with Disabilities Act and Florida Statute 286.26, the location of this public hearing is accessible to persons with disabilities. If you are a person with disability who needs any accommodation in order to participate in this proceeding, you are entitled, at no cost to you, to the provision of certain assistance. Interpreters for the hearing impaired (TTY 941-575-5013) or non-English speaking citizens, and any other special accommodations can be requested by contacting the Human Resources Manager/Non-Discrimination Coordinator whose address is 326 W. Marion Avenue, Punta Gorda, FL 33950, whose telephone number is (941) 575-3371, and whose email address is humres@cityofpuntagordafl.com, at least two (2) calendars days prior to the meeting. 2

Title: Approval of Minutes: Punta Gorda Isles Canal Advisory Committee Meeting of October 20, 2025. Funds: Recommended Action: Punta Gorda Isles Canal Advisory Committee approval. Summary: Regular Meetings Minutes of October 20, 2025 Department/Division: Public Works PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE CITY OF PUNTA GORDA 12/15/2025 APPROVAL OF MINUTES EXHIBITS: 1. October 20, 2025, Minutes 3

CITY OF PUNTA GORDA, FLORIDA PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE MEETING MINUTES OCTOBER 20, 2025, 1:30 P.M. 120 LAISHLEY COURT PUNTA GORDA, FL 33950 MEMBERS PRESENT: Robert Knabe, Chair Jeffrey D’Amico, Jake Dye, Ronald Ludvig MEMBERS ABSENT: Kenneth Rolland, Harry Walberg CITY STAFF PRESENT: Bryan Clemons, Engineering Manager; Marc Storm, Canal Maintenance Supervisor; Alexandra Friend, Board Recorder CALL TO ORDER Chair Knabe called the meeting to order at 1:30 p.m., followed by the Pledge of Allegiance. PUBLIC COMMENTS There were none. 1) APPROVAL OF MINUTES 1.a Approval of Minutes: Punta Gorda Isles Canal Advisory Committee Meeting of September 15, 2025. Exhibits: Cover Page September 15, 2025, Minutes Member Ludvig MOVED to approve the September 15, 2025, minutes, SECONDED by Member Dye. AYE: D'Amico, Dye, Knabe, Ludvig ABSENT: Rolland, Walberg MOTION CARRIED. 2) REPORTS 2.a Finance Report September 2025 Exhibits: Cover Page Punta Gorda Isles Canal Maintenance Expenditure Report 09302025 Punta Gorda Isles Canal Maintenance Revenue Report 009302025 Marc Storm, Canal Maintenance Supervisor, presented the report. 2.b Budget Utilization Report September 2025 Exhibits: Cover Page PGI Utilization 202509 4

Marc Storm presented the report. 2.c Seawall Replacement Status Report September 2025 Exhibits: Cover Page NE2_IAN Seawall Phase II_Replacement Status_090925 NW1_IAN Seawall Phase I_Replacement Status_090925 NW2_Seawall Phase II_Replacement Status_090925 SE_IAN Seawall Phase I_Replacement Status_090925 SW_IAN Seawall Phase II_Replacement Status_090925 IanSeawallStatusWithPhase2_PGI_Charts20250828 IanSeawallStatusMCG_Phase2_Chart20250828 IanSeawallStatusMCG_Chart20250828 Marc Storm presented the report. 2.d Permits Authorized by City Staff September 2025 Exhibits: Cover Page PGI Canal Maintenance Report by City Staff 09302025 Marc Storm presented the report. 2.e Punta Gorda Isles Capital Improvement Status Report September 2025 Exhibits: Cover Page PGI Capital Improvement Status 202509 Marc Storm presented the report. Discussion ensued regarding securing a spoil site and the challenges with same. 2.f Master Permit Agreement Status Report September 2025 Exhibits: Cover Page MasterPermitStatus202509PGI Marc Storm presented the report. 3) QUASI-JUDICIAL PUBLIC HEARINGS 3.a There are no Public Hearings for the October 20, 2025, meeting. Exhibits: Cover Page There were none. 4) GENERAL BUSINESS There was none. 5

STAFF COMMENTS There were none. MEMBER COMMENTS There were none. ADJOURNMENT The meeting adjourned at 1:30 p.m. Chair Board Recorder 6

Title: Finance Report November 2025 Funds: Recommended Action: For informational purposes only, no action required. Summary: The attached monthly report provides updates on Expenditures and Revenue Reports for Punta Gorda Isles. Department/Division: Public Works PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE CITY OF PUNTA GORDA 12/15/2025 REPORTS EXHIBITS: 1. Punta Gorda Isles Canal Maintenance Expenditure Report 11302025 2. Punta Gorda Isles Canal Maintenance Revenue Report 11302025 7

8

9

10

Title: Budget Utilization Report November 2025 Funds: Recommended Action: For information purposes only, no action required. Summary: The attached monthly report provides updates on monthly report of work completed and expenditures for seawall repairs and maintenance. Department/Division: Public Works PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE CITY OF PUNTA GORDA 12/15/2025 REPORTS EXHIBITS: 1. PGI Utilization 202512 11

City of PUNTA GORDA Florida REPORTING PERIOD AS OF: December 3, 2025 PUBLIC WORKS PGI CANAL MAINTENANCE 1075 MONTHLY REPORT OF WORK COMPLETED AND EXPENDITURES FOR SEAWALL R&M DESCRIPTION: ANNUAL SCHEDULED WORK AMENDED SCHEDULED WORK CURRENT MONTH WORK YTD COMP WORK % COMP REMAINING QUANTITY QUANTITY QUANTITY UNIT Nov-25 $6,950,000 $6,950,000 BUD $0 $0 0% $6,950,000 Seawall Panels/Supplies $749,700 $749,700 BUD $0 $0 0% $749,700 $5,815,600 $6,069,490 BUD $527,043 $527,043 9% $5,542,447 $67,120 $67,120 BUD $0 $0 0% $67,120 $60,000 $60,000 BUD $0 $0 0% $60,000 $30,000 $41,803 BUD $0 $0 0% $41,803 Inlet Dredging NOTE: City seawall program has 3 more SOW's to complete in 2025 with $1.5 million, rollover remaining into FY26 which is at $5.4 million. Hurricane Ian update still not processed for FEMA funds. Inlet dredging has some rollover from last year to this year. Some rollover funds availaible for spoil site project and seawall assessment in FY26 Spoil Site Channel Permitting/Seawall Assessment FY - 10/01/2025 - 09/30/2026 Seawall Replacement Mangrove Trimming Hurricane Ian Seawall Replacement J:\960 Canal Maintenance\PGI Monthly Reports\Budget Utilization Reports\2025-2026\PGI Utilization 202512 12

Title: Seawall Replacement Status Report November 2025. Funds: Recommended Action: For informational purposes only, no action required. Summary: The attached monthly report provides updates on the Punta Gorda Isles Seawall Replacement Work Program FY 2022/2023. Department/Division: Public Works PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE CITY OF PUNTA GORDA 12/15/2025 REPORTS EXHIBITS: 1. PGI seawall replacement 2512 2. IanSeawallStatusMCG_Phase1_Chart20251021 3. IanSeawallStatusMCG_Phase2_Chart20251021 4. IanSeawallStatusWithPhase2_PGI_Charts20251021 5. NE2_IAN Seawall Phase II_Replacement Status_120525 6. NW1_IAN Seawall Phase I_Replacement Status_120525 7. NW2_IAN Seawall Phase II_Replacement Status_120525 8. SE_IAN Seawall Phase I_Replacement Status_120525 9. SW_IAN Seawall Phase II_Replacement Status_120525 13

Seawall Maintenance Replacement FY 23/24 Start Week Location # Wall Priority Address Estimated Length Actual Length Status 5/9/2025 1 SEVERE SWAN CT 1230 84 83 C 5/27/2025 2 SEVERE CASEY KEY 1523,1531,1537/USSEPA CT 5005 172 172 C 12/3/2025 3 HIGH OSPREY DR 1351, 1355, 1359, 1362, 1358 541 U 1/15/2026 4 HIGH GULFVIEW RD 125, 135, 2101 117 LTR 1/29/2026 5 HIGH DARIN DR 3631 174 LTR TBD 6 HIGH CORONADO 1216 83 TBD 7 MED SABAL DR 15,19,23,27 295 TBD 8 MED LUCIA DR 802 197 TBD 9 MED ST KITTS CT 3805, 3811, 3817, 3823, 3829, 3833, 3839, 3846 /RYAN BLVD2611, 2523, BERMUDA CT 3800 931 TBD 10 MED BOCA RATON CT 1756,1764,1748,1772 264 TBD 11 MED PAMELA DR 702,704,720,730 486 TBD 12 MED PAMELA DR 701 74 TBD 13 MED SANTA BRIGIDA CT 910,920,930 255 TBD 14 MED RIO CT 2795 100 TBD 15 LOW TRINIDAD CT 3367, 3370 297 TBD 16 LOW GULFVIEW RD 158 86 TBD 17 LOW DIPPER CT 3518,3524,3530,3536/GREBE DR 1424, 1418, 1419 415 TBD 18 LOW RAVEN CT 1479,1485/SANDPIPER 3400,3408, 3414, /WREN 1478 258 TBD 19 LOW OSPREY CT 1304, 1310 278 TBD 20 LOW SEAFAN DR 1419 100 TBD 21 LOW CASEY KEY DR 1730, 1734, 1740, 1746, 1750, 1745, 1737 1209 TBD 22 LOW CROOKED ISLAND 3967, 3968, 3972 330 TBD 23 LOW SEABREEZE 1200 42 TBD 24 LOW DON QUIXOTE DR 2800, 2804 116 TBD 25 LOW LA SALINA CT 1100, /AQUI ESTA 2285, 2245 140 TBD 26 LOW SANCHO PANZA CT 2830, 2826, 2834 198 TBD 27 LOW TROPICANA 22, 26 170 TBD 28 LOW TROPICANA 70 75 TBD 29 LOW TROPICANA 123 104 TBD 30 LOW VIA ESPLANADE 801 86 TBD 31 LOW RIDING ROCKS 1244, 1234, 1234 229 TBD 32 LOW ELEUTHERA 522 75 TBD 33 LOW VIA TUNIS 712 107 TBD 34 LOW VIA TRIPOLI 1111, 1119, 1123 189 TBD 35 LOW MINEO 1335 135 TBD 36 LOW APPIAN DR 1605, 1615, 1625 142 TBD 37 LOW PARISIAN CT 2612, 2606 100 TBD 38 LOW PARISIAN CT 2642 93 Total 8747 255 LTR LETTER SENT U UNDER CONSTRUCTION MS 12/3/2025 C COMPLETE 14

Hurricane Ian Seawall Restoration Status 91.3% 81.7% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 9/14/2023 9/28/2023 10/12/2023 10/26/2023 11/9/2023 12/7/2023 12/21/2023 1/4/2024 1/18/2024 2/1/2024 2/15/2024 2/29/2024 3/14/2024 3/28/2024 4/11/2024 4/25/2024 5/9/2024 5/23/2024 6/6/2024 6/20/2024 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 5/30/2025 6/13/2025 6/27/2025 7/25/2025 8/28/2025 10/21/2025 Hurricane Ian Restoration Progress ‐ MCG BSI‐N, BSI‐S, PGI‐NW1, and PGI‐SE (Phase 1) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 15

Hurricane Ian Seawall Restoration Status 69.7% 54.6% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 5/30/2025 6/13/2025 6/27/2025 7/25/2025 8/28/2025 10/21/2025 Hurricane Ian Restoration Progress ‐ MCG PGI‐NE2, PGI‐NW2, and PGI‐SW (Phase 2) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 16

Hurricane Ian Seawall Restoration Status 81.7% 77.8% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 9/14/2023 9/28/2023 10/12/2023 10/26/2023 11/9/2023 12/7/2023 12/21/2023 1/4/2024 1/18/2024 2/1/2024 2/15/2024 2/29/2024 3/14/2024 3/28/2024 4/11/2024 4/25/2024 5/9/2024 5/23/2024 6/6/2024 6/20/2024 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 5/30/2025 6/13/2025 6/27/2025 7/25/2025 8/28/2025 10/21/2025 Hurricane Ian Restoration Progress ‐ PGI Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) % of time used is based on MCG Phase 1 contract end date. Other contractor zones have different end dates. Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 17

Hurricane Ian Seawall Restoration Status Contractor: Economy Contract completed, 12/5/2024 was the final meeting. 96.2% 100.0% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 110.0% 9/13/2023 9/28/2023 10/12/2023 10/26/2023 11/9/2023 12/7/2023 12/21/2023 1/4/2024 1/18/2024 2/1/2024 2/15/2024 2/29/2024 3/14/2024 3/28/2024 4/11/2024 4/25/2024 5/9/2024 5/23/2024 6/6/2024 6/20/2024 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 Hurricane Hurricane 10/24/2024 11/7/2024 11/21/2024 12/5/2024 Hurricane Ian Restoration Progress ‐ PGI‐NE1 Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 1/22/2025 Information based on Progress Meeting Minutes by Weiler Engineering 18

Hurricane Ian Seawall Restoration Status Contractor: RJ Gorman Contract cancelled, 6/6/2024 was the final meeting. 46.4% 104.0% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 110.0% 09/14/23 09/28/23 10/12/23 10/30/23 11/09/23 12/07/23 12/21/23 01/04/24 01/18/24 02/01/24 02/15/24 02/29/24 03/14/24 03/28/24 04/11/23 04/25/24 05/09/24 05/23/24 06/06/24 Hurricane Ian Restoration Progress ‐ PGI‐NE2 (Phase 1) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 1/22/2025 Information based on Progress Meeting Minutes by Weiler Engineering 19

Hurricane Ian Seawall Restoration Status Contractor: MCG 68.9% 48.7% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 5/30/2025 6/13/2025 6/27/2025 7/25/2025 8/28/2025 10/21/2025 Hurricane Ian Restoration Progress ‐ PGI‐NE2 (Phase 2) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 20

Hurricane Ian Seawall Restoration Status Contractor: MCG 81.3% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 9/14/2023 9/28/2023 10/12/2023 10/26/2023 11/9/2023 12/7/2023 12/21/2023 1/4/2024 1/18/2024 2/1/2024 2/15/2024 2/29/2024 3/14/2024 3/28/2024 4/11/2024 4/25/2024 5/9/2024 5/23/2024 6/6/2024 6/20/2024 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 5/30/2025 6/13/2025 6/27/2025 7/25/2025 8/28/2025 10/21/2025 Hurricane Ian Restoration Progress ‐ PGI‐NW1 Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 21

Hurricane Ian Seawall Restoration Status Contractor: RJ Gorman Contract cancelled, 6/6/2024 was the final meeting. 20.5% 104.0% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 110.0% 09/14/23 09/28/23 10/12/23 10/30/23 11/09/23 12/07/23 12/21/23 01/04/24 01/18/24 02/01/24 02/15/24 02/29/24 03/14/24 03/28/24 04/11/23 04/25/24 05/09/24 05/23/24 06/06/24 Hurricane Ian Restoration Progress ‐ PGI‐NW2 (Phase 1) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 1/22/2025 Information based on Progress Meeting Minutes by Weiler Engineering 22

Hurricane Ian Seawall Restoration Status Contractor: MCG 68.9% 55.9% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 5/30/2025 6/13/2025 6/27/2025 7/25/2025 8/28/2025 10/21/2025 Hurricane Ian Restoration Progress ‐ PGI‐NW2 (Phase 2) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 23

Hurricane Ian Seawall Restoration Status Contractor: MCG Zone completed, no further updates. 100.7% 76.8% 0.0% 20.0% 40.0% 60.0% 80.0% 100.0% 9/14/2023 9/28/2023 10/12/2023 10/26/2023 11/9/2023 12/7/2023 12/21/2023 1/4/2024 1/18/2024 2/1/2024 2/15/2024 2/29/2024 3/14/2024 3/28/2024 4/11/2024 4/25/2024 5/9/2024 5/23/2024 6/6/2024 6/20/2024 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 Hurricane Ian Restoration Progress ‐ PGI‐SE Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 24

Hurricane Ian Seawall Restoration Status Contractor: RJ Gorman Contract cancelled, 6/6/2024 was the final meeting. 24.3% 104.0% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 110.0% 09/14/23 09/28/23 10/12/23 10/30/23 11/09/23 12/07/23 12/21/23 01/04/24 01/18/24 02/01/24 02/15/24 02/29/24 03/14/24 03/28/24 04/11/23 04/25/24 05/09/24 05/23/24 06/06/24 Hurricane Ian Restoration Progress ‐ PGI‐SW (Phase 1) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 1/22/2025 Information based on Progress Meeting Minutes by Weiler Engineering 25

Hurricane Ian Seawall Restoration Status Contractor: MCG 68.9% 55.6% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% 7/18/2024 8/1/2024 8/15/2024 8/29/2024 9/12/2024 9/30/2024 Hurricane 10/24/2024 11/7/2024 11/21/2024 Cancelled 12/19/2024 Cancelled 1/16/2025 1/31/2025 2/14/2025 3/7/2025 Cancelled 3/28/2025 4/11/2025 5/2/2025 5/16/2025 5/30/2025 6/13/2025 6/27/2025 7/25/2025 8/28/2025 10/21/2025 Hurricane Ian Restoration Progress ‐ PGI‐SW (Phase 2) Approx. % of Total Seawall % of Time Used Linear (Approx. % of Total Seawall) Linear (% of Time Used) Generated from IanSeawallStatusWithPhase2.xlsx, Summary tab on 11/5/2025 26

START WEEK OF LOCATION # WALL PRIORITY ADDRESS ESTIMATED LENGTH ACTUAL LENGTH STATUS 2003 LOW DON JUAN CT 915/925/935 132 133 C 2012 MED BRENDA CT 704 96 124 C 2002 LOW SAN MARINO CT 1580 182 U 2028 LOW BAL HARBOR BLVD 416 80 79 U 2018 LOW BAL HARBOR BLVD 740/760 74 66 U 2016 LOW APPIAN DR 1500/1510 37 30 U 2020 LOW VIA BIANCA 1600/1601 160 U 2022 LOW VIA BIANCA 1660 48 U 2007 LOW VIA TUNIS 601 201 U TOTAL 1795 1167 LTR Letter sent U Under Construction C Complete HN Home owner notified Revised 12/5/25 MARINE CONTRACTING GROUP PHASE II NE2 - SEAWALL REPLACEMENT WORK PROGRAM FY 2024/2025 27

START WEEK OF LOCATION # WALL PRIORITY ADDRESS ESTIMATED LENGTH ACTUAL LENGTH STATUS 28

START WEEK OF WALL PRIORITY LOCATION ADDRESS ESTIMATED LENGTH ACTUAL LENGTH STATUS Low 3017 CORAL WAY 2886 2892 84 77 C Low 3054 COLONY POINT DR 168 174 178 184 244 240 C Low 3019 CORAL WAY 2813 2815 82 83 U Low 3018 CORAL WAY 2833 80 99 U Low 3055 COLONY POINT DR 76 80 100 99 U Low 3056 COLONY POINT DR 28 32 108 106 U Low 3057 COLONY POINT DR 1 247 U 12/15/25 Low 3009 AQUA CT 2755 2775 2795 106 Ltr 12/22/25 Low 3005 TROPICANA DR 14 85 Ltr TOTAL 7716 7172 LTR Letter sent U Under Construction C Complete HN Home owner notified Revised 12/5/25 NW1 - SEAWALL REPLACEMENT WORK PROGRAM FY 2023/2024/2025 MARINE CONTRACTING GROUP PHASE I 29

START WEEK OF WALL PRIORITY LOCATION # ADDRESS ESTIMATED LENGTH ACTUAL LENGTH STATUS LOW 4048 BAYVIEW RD 2210 30 87 C LOW 4002 JAMAICA WAY 1771 96 89 C MED 4053 SIERRA LN 2449/2435 - Birds nest delaying 98 151 U LOW 4001 JAMAICA WAY 2035/2025/2015 313 317 U LOW 4046 GULFVIEW RD 118/110 90 103 U LOW 4045 GULFVIEW RD 182/174/166 170 U LOW 4007 MARIA CT 179/183 82 U LOW 4023 VIA SEVILLE 2141/2181 112 U LOW 4024 VIA SEVILLE 2080/2100/2140 100 U 12/8/25 LOW 4026 EL CERITO CT 2237/2255/2275 156 Ltr 12/22/25 LOW 4027 EL CERITO CT 2111 80 Ltr 12/29/25 LOW 4029 BELVEDERE CT 511/517 97 Ltr 1/5/26 LOW 4032 BELVEDERE CT 280/290 53 1/12/26 LOW 4034 DE LIDO CT 341/361 107 1/19/26 LOW 4035 DE LIDO CT 381 69 1/26/26 LOW 4036 DE LIDO CT 399 45 2/2/26 LOW 4037 DE LIDO CT 380/399 54 2/9/26 LOW 4040 BELAIRE CT 255 80 2/16/26 LOW 4041 BELAIRE CT 355/365/375 88 12/8/25 LOW 4010 BOCA RATON CT 1751/1743 142 Ltr 12/22/25 LOW 4011 BELLE CT 1799/1797 220 Ltr 1/12/26 LOW 4012 BELLE CT 1793 138 1/26/26 LOW 4013 BAL HARBOR BLVD 515/533/551 104 TOTAL 5019 3463 LTR Letter sent U Under Construction C Complete HN Home owner notified Revised 12/5/25 MARINE CONTRACTING GROUP PHASE II NW2 - SEAWALL REPLACEMENT WORK PROGRAM FY 2024/2025 30

START WEEK OF WALL PRIORITY LOCATION ADDRESS ESTIMATED LENGTH ACTUAL LENGTH STATUS Low 5015 WAXWING CT 1406 100 U TOTAL 4152 4181 U Under Construction C Complete LTR Letter sent Revised 12/5/25 SE - SEAWALL REPLACEMENT WORK PROGRAM FY 2023/2024/2025 MARINE CONTRACTING GROUP PHASE I 31

START WEEK OF WALL PRIORITY LOCATION # ADDRESS ESTIMATED LENGTH ACTUAL LENGTH STATUS LOW 6042 RYAN BLVD 2750 170 172 C LOW 6045 LA COSTA ISLAND CT 3900/3906 126 137 C LOW 6044 AVES ISLAND CT 3835 130 127 C LOW 6038 CARMICHAEL DR 3649/3701 134 126 U LOW 6039 BONAIRE CT 3623/3617 111 U LOW 6040 ARUBA CT 3652/3658/3664/3670 185 U 12/15/25 LOW 6028 DEBORAH DR 2216/2224 90 Ltr 12/22/25 LOW 6029 DEBORAH DR 2240/2246/2300 102 Ltr 12/29/25 LOW 6030 ST DAVIDS ISLAND CT 2361/2349 52 Ltr 1/5/26 LOW 6024 GRENADA CT 3338 44 1/12/26 LOW 6023 GRENADA CT 3341/3345 278 1/26/26 LOW 6011 SOCORRO DR 1129/1135 52 12/8/25 LOW 6019 ANTIGUA DR 3200/3205 107 Ltr 12/29/25 LOW 6018 ANTIGUA DR 3200/3206 193 Ltr 1/12/26 LOW 6017 MAYAGUANA CT 2737/2740 185 1/26/26 LOW 6007 LA SALINA CT 1117/1123/1127/1131/1135 148 2/9/26 LOW 6008 LA SALINA CT 1134/1140 186 TOTAL 3824 2059 LTR Letter sent U Under Construction C Complete HN Home owner notified Revised 12/5/25 MARINE CONTRACTING GROUP PHASE II SW - SEAWALL REPLACEMENT WORK PROGRAM FY 2024/2025 32

Title: Permits Authorized by City Staff November 2025. Funds: Recommended Action: No action required for informational purposes only. Summary: The monthly report provides updates on permits provided by City Staff. Department/Division: Public Works PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE CITY OF PUNTA GORDA 12/15/2025 REPORTS EXHIBITS: 1. PGI Canal Maintenance Report by City Staff 11302025 33

Date: 12/10/2025 PGI Canal Maintenance Report Page 1 App Yr App Number Appl Type Appl Date Application Description Street No. Str Dir Street Name Str Suff Lot Block Sub Div Sec 25 196116 BCNL 11/3/2025 CALL FOR FINAL ONCE COMPLETED 1457 SURFBIRD CT 0224 0014 PGI 014 BCNL 11/3/2025 INSTALLATION OF THREE NEW BUMPER 1457 SURFBIRD CT 0224 0014 PGI 014 BCNL 11/3/2025 PILINGS, STRAIGHTEN THREE BUMPER PILINGS 1457 SURFBIRD CT 0224 0014 PGI 014 BCNL 11/3/2025 11/3/2025, 12:30:41 PM APASTOR 1457 SURFBIRD CT 0224 0014 PGI 014 196119 BCNL 11/3/2025 ***NOC ENCLOSED W/ PERMIT*** 2571 BRAZILIA CT 0047 0018 PGI 006 BCNL 11/3/2025 CALL FOR FINAL ONCE COMPLETED 2571 BRAZILIA CT 0047 0018 PGI 006 BCNL 11/3/2025 HOMEOWNER HIRING LIVINGSTON ELECTRIC 2571 BRAZILIA CT 0047 0018 PGI 006 BCNL 11/3/2025 INDEPENDENTLY OF MCG FOR ALL ELECTRICAL 2571 BRAZILIA CT 0047 0018 PGI 006 BCNL 11/3/2025 INSTALLATION OF BOAT LIFT 2571 BRAZILIA CT 0047 0018 PGI 006 BCNL 11/3/2025 WORK 2571 BRAZILIA CT 0047 0018 PGI 006 BCNL 11/3/2025 11/3/2025, 2:39:13 PM APASTOR 2571 BRAZILIA CT 0047 0018 PGI 006 196129 BCNL 11/4/2025 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 **NO HARD FILE** NOC ATTACHED 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 ADDED DIMENSION OF DOCK, THANK YOU. 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 CALL FOR FINAL ONCE JOB IS COMPLETED 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 HOMEOWNER IS HIRING ALLIANCE REPAIR & 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 INSTALL DOCK AND BOAT LIFT 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 MAINTENANCE INDEPENDETLY OF MCG TO 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 PERFORM ALL ELECTRICAL WORK 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 11/19/2025, 3:12:06 PM SCARLAW 2240 VIA VENICE 0027 0023 PGI 005 BCNL 11/4/2025 11/4/2025, 9:43:49 AM SCARLAW 2240 VIA VENICE 0027 0023 PGI 005 196148 BCNL 11/5/2025 ***NOC ATTACHED*** 1361 WILLET CT 0213 0005 PGI 014 BCNL 11/5/2025 **ELECTRICAL: THE BOAT LIFT PROS 1361 WILLET CT 0213 0005 PGI 014 BCNL 11/5/2025 CALL FOR FINAL ONCE COMPLETED 1361 WILLET CT 0213 0005 PGI 014 BCNL 11/5/2025 INSTALL NEW 13K LIFT AND NEW PILINGS 1361 WILLET CT 0213 0005 PGI 014 BCNL 11/5/2025 11/5/2025, 9:17:23 AM APASTOR 1361 WILLET CT 0213 0005 PGI 014 196175 BCNL 11/6/2025 CALL FOR FINAL ONCE COMPLETED 2600 VIA VENETO 0055 0004 PGI 006 BCNL 11/6/2025 REMOVAL OF BOATLIFT AND ITS FOUR PILINGS 2600 VIA VENETO 0055 0004 PGI 006 BCNL 11/6/2025 11/6/2025, 12:03:02 PM APASTOR 2600 VIA VENETO 0055 0004 PGI 006 196185 BCNL 11/7/2025 CALL FOR FINAL INSPECTION WHEN JOB 1014 FRANCESCACT 0083 0019 PGI 007 34

Date: 12/10/2025 PGI Canal Maintenance Report Page 2 App Yr App Number Appl Type Appl Date Application Description Street No. Str Dir Street Name Str Suff Lot Block Sub Div Sec 25 196185 BCNL 11/7/2025 COMPLETED 1014 FRANCESCACT 0083 0019 PGI 007 BCNL 11/7/2025 CONTRACTOR NEEDS TO RENEW PRIOR TO ISSUE 1014 FRANCESCACT 0083 0019 PGI 007 BCNL 11/7/2025 NEED NOC PRIOR TO FIRST INSPECTION 1014 FRANCESCACT 0083 0019 PGI 007 BCNL 11/7/2025 REINSTALL BOAT LIFT WITH 4 NEW PILINGS 1014 FRANCESCACT 0083 0019 PGI 007 BCNL 11/7/2025 11/7/2025, 8:44:20 AM LGRANGER 1014 FRANCESCACT 0083 0019 PGI 007 196193 BCNL 11/7/2025 ***NOC ENCLOSED W/ PERMIT*** 30 OCEAN DR 0011 0013 PGI 004 BCNL 11/7/2025 CALL FOR FINAL ONCE COMPLETED 30 OCEAN DR 0011 0013 PGI 004 BCNL 11/7/2025 INSTALLATION OF DOCK EXTENSIONS 30 OCEAN DR 0011 0013 PGI 004 BCNL 11/7/2025 11/7/2025, 11:59:47 AM APASTOR 30 OCEAN DR 0011 0013 PGI 004 196195 BCNL 11/7/2025 CALL FOR FINAL INSPECTION WHEN JOB 1251 PARTRIDGE DR 0217 0015 PGI 014 BCNL 11/7/2025 COMPLETED 1251 PARTRIDGE DR 0217 0015 PGI 014 BCNL 11/7/2025 INSTALL USED BOAT LIFT ON EXISTING 1251 PARTRIDGE DR 0217 0015 PGI 014 BCNL 11/7/2025 PILINGS 1251 PARTRIDGE DR 0217 0015 PGI 014 BCNL 11/7/2025 11/7/2025, 1:52:48 PM LGRANGER 1251 PARTRIDGE DR 0217 0015 PGI 014 196196 BCNL 11/7/2025 **NO HARD FILE** 3256 WHITE IBIS CT 0180 0013 PGI 014 BCNL 11/7/2025 CALL FOR FINAL ONCEN JOB IS FINISHED 3256 WHITE IBIS CT 0180 0013 PGI 014 BCNL 11/7/2025 REPLACE MOORING PILINGS -SLIP #7 3256 WHITE IBIS CT 0180 0013 PGI 014 BCNL 11/7/2025 11/7/2025, 2:10:17 PM SCARLAW 3256 WHITE IBIS CT 0180 0013 PGI 014 196197 BCNL 11/7/2025 CALL FOR FINAL INSPECTION WHEN JOB 1206 RIDING ROCKSLN 0106 0011 PGI 011 BCNL 11/7/2025 COMPLETED 1206 RIDING ROCKSLN 0106 0011 PGI 011 BCNL 11/7/2025 INSTALL DOLPHIN MODEL 212 #25000 BOAT 1206 RIDING ROCKSLN 0106 0011 PGI 011 BCNL 11/7/2025 INSTALL 2- 7'X22.5' CONCRETE DOCK 1206 RIDING ROCKSLN 0106 0011 PGI 011 BCNL 11/7/2025 LIFT 1206 RIDING ROCKSLN 0106 0011 PGI 011 BCNL 11/7/2025 NOC WITH APPLICATION 1206 RIDING ROCKSLN 0106 0011 PGI 011 BCNL 11/7/2025 11/7/2025, 2:21:58 PM LGRANGER 1206 RIDING ROCKSLN 0106 0011 PGI 011 196198 BCNL 11/7/2025 CALL FOR FINAL INSPECTION WHEN JOB 2824 CORAL WAY0020 0006 PGI 002 BCNL 11/7/2025 CHECK FOR ANY ELECTRICAL WORK NOT 2824 CORAL WAY0020 0006 PGI 002 BCNL 11/7/2025 COMPLETED 2824 CORAL WAY0020 0006 PGI 002 BCNL 11/7/2025 CONCRETE DOCK 2824 CORAL WAY0020 0006 PGI 002 BCNL 11/7/2025 INCLUDED ON THIS PERMIT 2824 CORAL WAY0020 0006 PGI 002 35

Date: 12/10/2025 PGI Canal Maintenance Report Page 3 App Yr App Number Appl Type Appl Date Application Description Street No. Str Dir Street Name Str Suff Lot Block Sub Div Sec 25 196198 BCNL 11/7/2025 REPLACE EXISTING DOCK WITH A 7' X 30' 2824 CORAL WAY0020 0006 PGI 002 BCNL 11/7/2025 11/7/2025, 2:31:08 PM LGRANGER 2824 CORAL WAY0020 0006 PGI 002 196199 BCNL 11/7/2025 CALL FOR FINAL INSPECTION WHEN JOB 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 BCNL 11/7/2025 COMPLETED 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 BCNL 11/7/2025 CONCRETE DOCK 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 BCNL 11/7/2025 INCLUDED WITH PERMIT 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 BCNL 11/7/2025 NOC WITH APPLICATION 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 BCNL 11/7/2025 PLEASE CHECK FOR ELECTRICAL WORK NOT 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 BCNL 11/7/2025 REPLACED EXISTING DOCKS WITH A 7' X 30' 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 BCNL 11/7/2025 11/7/2025, 2:35:50 PM LGRANGER 3756 WHIP-POOR-WILLBLVD0208 0027 PGI 014 196202 BCNL 11/7/2025 CALL FOR FINAL INSPECTION WHEN JOB 8 OCEAN DR 0011 0018 PGI 004 BCNL 11/7/2025 COMPLETED 8 OCEAN DR 0011 0018 PGI 004 BCNL 11/7/2025 DOLPHIN MODEL 209 8 OCEAN DR 0011 0018 PGI 004 BCNL 11/7/2025 INSTALL 8'X74' CONCRETE DOCK, INSTALL 8 OCEAN DR 0011 0018 PGI 004 BCNL 11/7/2025 NOC WITH APPLICATION 8 OCEAN DR 0011 0018 PGI 004 BCNL 11/7/2025 11/7/2025, 2:55:38 PM LGRANGER 8 OCEAN DR 0011 0018 PGI 004 196208 BCNL 11/10/2025 **NO HARD FILE** NOC ATTACHED 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 BOAT LIFT 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 CALL FOR FINAL ONCE JOB IS COMPLETED 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 ELE SUB IS MATHEIS ELE 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 HOMEOWNER HIRING MATHEIS ELECTRIC 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 INDEPENDENTLY OF MCG FOR ALL ELECTRICAL 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 REPLACE BOAT LIFT- USING OWNER SUPPLIED 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 WORK 2261 BAYVIEW RD 0004 0015 PGI 004 BCNL 11/10/2025 11/10/2025, 8:53:39 AM SCARLAW 2261 BAYVIEW RD 0004 0015 PGI 004 196213 BCNL 11/10/2025 **NO HARD FILE** NOC ASTTACHED 379 BAL HARBORBLVD0036 0005 PGI 005 BCNL 11/10/2025 BOAT LIFT 379 BAL HARBORBLVD0036 0005 PGI 005 BCNL 11/10/2025 CALL FOR FINAL ONCE JOB IS COMPLETED 379 BAL HARBORBLVD0036 0005 PGI 005 BCNL 11/10/2025 HOMEOWNER HIRING LIVINGSTON ELECTRIC 379 BAL HARBORBLVD0036 0005 PGI 005 BCNL 11/10/2025 INDEPENDENTLY OF MCG FOR ALL ELECTRICAL 379 BAL HARBORBLVD0036 0005 PGI 005 36

Date: 12/10/2025 PGI Canal Maintenance Report Page 4 App Yr App Number Appl Type Appl Date Application Description Street No. Str Dir Street Name Str Suff Lot Block Sub Div Sec 25 196213 BCNL 11/10/2025 INSTALLATION OF DOCK AND DOWNER SUPPLIED 379 BAL HARBORBLVD0036 0005 PGI 005 BCNL 11/10/2025 WORK 379 BAL HARBORBLVD0036 0005 PGI 005 BCNL 11/10/2025 11/10/2025, 12:19:42 PM SCARLAW 379 BAL HARBORBLVD0036 0005 PGI 005 196324 BCNL 11/20/2025 **NO HARD FILE**NOC WITH PERMIT** 3900 LA COSTA ISLANDCT 0142 0007 PGI 012 BCNL 11/20/2025 CALL FOR FINAL ONCE JOB IS COMPLETED 3900 LA COSTA ISLANDCT 0142 0007 PGI 012 BCNL 11/20/2025 INSTALLATION OF TWO PILINGS FOR MOORING 3900 LA COSTA ISLANDCT 0142 0007 PGI 012 BCNL 11/20/2025 PILINGS 3900 LA COSTA ISLANDCT 0142 0007 PGI 012 BCNL 11/20/2025 SYSTEM ALSO REMOVAL OF TWO OUTER LIFT 3900 LA COSTA ISLANDCT 0142 0007 PGI 012 BCNL 11/20/2025 11/20/2025, 8:37:35 AM SCARLAW 3900 LA COSTA ISLANDCT 0142 0007 PGI 012 196333 BCNL 11/20/2025 ***NOC ENCLOSED W/ PERMIT*** 1620 SEA HAVEN DR 0000 00TE PGI 09B BCNL 11/20/2025 CALL FOR FINAL ONCE COMPLETED 1620 SEA HAVEN DR 0000 00TE PGI 09B BCNL 11/20/2025 ELECTRICAL WORK 1620 SEA HAVEN DR 0000 00TE PGI 09B BCNL 11/20/2025 HOMEOWNER HIRING LIVINGSTON ELECTRIC 1620 SEA HAVEN DR 0000 00TE PGI 09B BCNL 11/20/2025 INDEPENDENTLY OF MCG TO PERFORM ALL 1620 SEA HAVEN DR 0000 00TE PGI 09B BCNL 11/20/2025 INSTALLATION OF BOAT LIFT ON EXISITNG 1620 SEA HAVEN DR 0000 00TE PGI 09B BCNL 11/20/2025 PILINGS - SLIP 24 1620 SEA HAVEN DR 0000 00TE PGI 09B BCNL 11/20/2025 11/20/2025, 11:48:13 AM APASTOR 1620 SEA HAVEN DR 0000 00TE PGI 09B 196334 BCNL 11/20/2025 ***NOC ENCLOSED W/ PERMIT*** 1405 BLUE JAY CT 0197 0016 PGI 014 BCNL 11/20/2025 CALL FOR FINAL ONCE COMPLETED 1405 BLUE JAY CT 0197 0016 PGI 014 BCNL 11/20/2025 REPLACE SECTION OF DOCK 1405 BLUE JAY CT 0197 0016 PGI 014 BCNL 11/20/2025 11/20/2025, 11:56:13 AM APASTOR 1405 BLUE JAY CT 0197 0016 PGI 014 196343 BCNL 11/21/2025 **NO HARD FILE** NOC ATTACHED 1625 COMPASS POINTECT T00E 0000 PGI 09B BCNL 11/21/2025 ELE SUB IS LIVINGSTON ELECTRIC 1625 COMPASS POINTECT T00E 0000 PGI 09B BCNL 11/21/2025 INSTALLATION OF TBOAT LIFT ON EXISTING 1625 COMPASS POINTECT T00E 0000 PGI 09B BCNL 11/21/2025 PILINGS-SLIP 26 1625 COMPASS POINTECT T00E 0000 PGI 09B BCNL 11/21/2025 11/21/2025, 11:30:42 AM SCARLAW 1625 COMPASS POINTECT T00E 0000 PGI 09B 196351 BCNL 11/21/2025 ***NOC ENCLOSED W/ PERMIT** 2795 LUNA CT 0018 0009 PGI 002 BCNL 11/21/2025 **ELECTRCAL: ELECTRICAL SOLUTIONS OF SWF 2795 LUNA CT 0018 0009 PGI 002 BCNL 11/21/2025 BOAT LIFT REMOVAL AND ADD 3 MOORING 2795 LUNA CT 0018 0009 PGI 002 BCNL 11/21/2025 CALL FOR FINAL ONCE COMPLETED 2795 LUNA CT 0018 0009 PGI 002 37

Date: 12/10/2025 PGI Canal Maintenance Report Page 5 App Yr App Number Appl Type Appl Date Application Description Street No. Str Dir Street Name Str Suff Lot Block Sub Div Sec 25 196351 BCNL 11/21/2025 PILING 2795 LUNA CT 0018 0009 PGI 002 BCNL 11/21/2025 11/21/2025, 3:32:38 PM APASTOR 2795 LUNA CT 0018 0009 PGI 002 196375 BCNL 11/25/2025 CALL FOR FINAL INSPECTION WHEN JOB 424 VIA CINTIA 0063 0006 PGI 007 BCNL 11/25/2025 COMPLETED 424 VIA CINTIA 0063 0006 PGI 007 BCNL 11/25/2025 NOC WITH APPLICATION 424 VIA CINTIA 0063 0006 PGI 007 BCNL 11/25/2025 REPLACE EXISTING LIFT WITH DOLPHIN MODEL 424 VIA CINTIA 0063 0006 PGI 007 BCNL 11/25/2025 11/25/2025, 11:03:16 AM LGRANGER 424 VIA CINTIA 0063 0006 PGI 007 BCNL 11/25/2025 202 7,000# BOAT LIFT 424 VIA CINTIA 0063 0006 PGI 007 196377 BCNL 11/25/2025 CALL FOR FINAL INSPECTION WHEN JOB 3805 BERMUDA CT 0136 0002 PGI 012 BCNL 11/25/2025 COMPLETED 3805 BERMUDA CT 0136 0002 PGI 012 BCNL 11/25/2025 NOC WITH APPLICATION 3805 BERMUDA CT 0136 0002 PGI 012 BCNL 11/25/2025 REPLACE EXISTING LIFT WITH DOLPHIN MODEL 3805 BERMUDA CT 0136 0002 PGI 012 BCNL 11/25/2025 11/25/2025, 11:20:45 AM LGRANGER 3805 BERMUDA CT 0136 0002 PGI 012 BCNL 11/25/2025 205 10,000# LIFT 3805 BERMUDA CT 0136 0002 PGI 012 196378 BCNL 11/25/2025 CALL FOR FINAL INSPECTION WHEN JOB 500 MATARES DR 0064 0010 PGI 007 BCNL 11/25/2025 COMPLETED 500 MATARES DR 0064 0010 PGI 007 BCNL 11/25/2025 CONCRETE DOCK 500 MATARES DR 0064 0010 PGI 007 BCNL 11/25/2025 NOC WITH APPLICATION 500 MATARES DR 0064 0010 PGI 007 BCNL 11/25/2025 REPLACE EXISTING DOCK W/ A 7'X33' 500 MATARES DR 0064 0010 PGI 007 BCNL 11/25/2025 11/25/2025, 11:26:05 AM LGRANGER 500 MATARES DR 0064 0010 PGI 007 196380 BCNL 11/25/2025 CALL FOR FINAL INSPECTION WHEN JOB 1446 KITTIWAKE DR 0211 0008 PGI 014 BCNL 11/25/2025 COMPLETED 1446 KITTIWAKE DR 0211 0008 PGI 014 BCNL 11/25/2025 CONCRETE DOCK 1446 KITTIWAKE DR 0211 0008 PGI 014 BCNL 11/25/2025 NOC WITH APPLICATION 1446 KITTIWAKE DR 0211 0008 PGI 014 BCNL 11/25/2025 REPLACE EXISTING DOCK WITH A 7'X90' 1446 KITTIWAKE DR 0211 0008 PGI 014 BCNL 11/25/2025 11/25/2025, 11:29:43 AM LGRANGER 1446 KITTIWAKE DR 0211 0008 PGI 014 196381 BCNL 11/25/2025 CALL FOR FINAL INSPECTION WHEN JOB 125 HIBISCUS DR 0018 0024 PGI 002 BCNL 11/25/2025 COMPLETED 125 HIBISCUS DR 0018 0024 PGI 002 BCNL 11/25/2025 CONCRETE DOCK 125 HIBISCUS DR 0018 0024 PGI 002 BCNL 11/25/2025 NOC WITH APPLICATION 125 HIBISCUS DR 0018 0024 PGI 002 38

Date: 12/10/2025 PGI Canal Maintenance Report Page 6 App Yr App Number Appl Type Appl Date Application Description Street No. Str Dir Street Name Str Suff Lot Block Sub Div Sec 25 196381 BCNL 11/25/2025 REPLACE EXISTING DOCK WITH A 7'X70' 125 HIBISCUS DR 0018 0024 PGI 002 BCNL 11/25/2025 11/25/2025, 11:34:28 AM LGRANGER 125 HIBISCUS DR 0018 0024 PGI 002 196385 BCNL 11/25/2025 **NO HARD FILE** NOC ATTACHED TO PERMIT 720 BIMINI LN 0098 0015 PGI 011 BCNL 11/25/2025 CALL FOR FINAL ONCE JOB IS COMPLETED 720 BIMINI LN 0098 0015 PGI 011 BCNL 11/25/2025 HOMEOWNER HIRING LIVINGSTON ELECTRIC TO 720 BIMINI LN 0098 0015 PGI 011 BCNL 11/25/2025 INDEPENDENTLY OF MCG 720 BIMINI LN 0098 0015 PGI 011 BCNL 11/25/2025 INSTALLATION OF BOAT LIFT 720 BIMINI LN 0098 0015 PGI 011 BCNL 11/25/2025 PERFORM ALL ELECTRICAL WORK 720 BIMINI LN 0098 0015 PGI 011 BCNL 11/25/2025 11/25/2025, 12:50:22 PM SCARLAW 720 BIMINI LN 0098 0015 PGI 011 39

Title: Punta Gorda Isles Capital Improvement Status Report November 2025. Funds: Recommended Action: For informational purposes only, no action required. Summary: The attached monthly report provides updates on Punta Gorda Isles Canal Maintenance Capital Improvement Program. Department/Division: Public Works PUNTA GORDA ISLES CANAL ADVISORY COMMITTEE CITY OF PUNTA GORDA 12/15/2025 REPORTS EXHIBITS: 1. PGI Captial Improvement Status 202512 40

Official record

ArtifactSourceState
AgendaNot published in the sources we holdunavailable
BudgetNot published in the sources we holdunavailable
Action agendaNot published in the sources we holdunavailable
MinutesNot published in the sources we holdunavailable
Transcript or captionsNot published in the sources we holdunavailable
AttachmentNot published in the sources we holdunavailable

Official pages

Coverage and corrections

Records considered

  • Punta Gorda Isles Canal Advisory Committee — Packet

Not claimed by this page

  • Verified meeting decisions with item-specific public-source evidence
  • Item-level plain-language summaries are not available; this page does not infer individual agenda items.
  • Item-linked, attributed deliberation
  • A source-grounded next meeting date
  • A plain-English overview is not available.
  • Official outcomes have not been published.
  • A transcript is not available.
  • No audio or video recording is linked.
  • Speakers have not been reliably matched to public profiles.
  • Named people and places have not been reliably resolved.
  • An individual roll-call roster is not available.

No source correction or revision history is recorded for this meeting. A corrected artifact will appear here as a new version rather than replacing what is shown above.

Canonical record: 536d31caa4bec54028354d6dae12a4cf. This page changes as stronger artifacts are published; it never overwrites an agenda with minutes.

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record