Read. Follow. Verify.North Carolina Prohibits Passing Data Center Energy Costs to Ratepayers and Creates Planning Commission
Last action · April 14, 2025: Ref To Com On Rules, Calendar, and Operations of the House (House action)Sponsors: Pricey Harrison and 9 others
Track this bill to get notified when it advances a stage. One tap to stop, anytime.
What This Bill Would Do
North Carolina House Bill 1002 prohibits public utilities from passing grid upgrade, generation, and fuel costs incurred for s onto regular ratepayers, unless charged directly to the data centers or based on electric demand. The bill also establishes a 14-member Special Commission for Data Center Planning to review energy supply, recommend grid expansions, and report its findings before expiring on June 30, 2027.
Residential and small business utility customers are shielded from paying for the substantial electrical infrastructure upgrades required by large data centers operating within the state.
- Commercial data centers have expanded rapidly in recent years, creating unprecedented demands on regional electrical grids and energy generation infrastructure. context
- Utility rate structures traditionally distribute infrastructure upgrade costs across all customer classes unless specific regulatory exceptions are enacted. context
Who It Would Affect
Groups the bill's text would affect if enacted, as described in the record. Being affected is not a position for or against it.
Public utilities
Public utilities are prohibited from including commercial data center grid and fuel upgrade costs in general ratepayer charges.
Commercial data centers
Commercial data centers face direct charges or prorated cost recovery models for the electric demand and grid upgrades they generate.
Electric service ratepayers
Ratepayers are protected from absorbing utility costs incurred solely for serving commercial data center facilities.
Key Facts
- Defines a commercial data center as a facility or array of facilities with a peak demand of 100 megawatts or greater.
- Prohibits public utilities from including increased fuel requirements, generation costs, and grid upgrade costs for data centers in rates approved for general ratepayers.
- Permits public utilities to charge data centers directly or prorate costs based on actual electric demand.
- Establishes a 14-member Special Commission for Data Center Planning consisting of gubernatorial, legislative, and agency appointees.
Show all 8 facts
- Directs the Commission to review grid capacity, examine artificial intelligence trends, survey corporate employers, and propose related legislation.
- Grants the Commission powers to hold public hearings, enter into contracts, and request testimony and documents from State agencies.
- Requires the Commission to submit a written report of its findings to leadership no later than three months after its last meeting.
- Sets an expiration date of June 30, 2027, for the Special Commission for Data Center Planning, at which point it will be abolished.
Frequently Asked Questions
What qualifies as a commercial data center under this bill?
Can utilities still recover the costs of serving data centers?
Who serves on the Special Commission for Data Center Planning?
When does the Special Commission expire?
What else do you want to know?
News Coverage
Follow the record
Votes, people, money & the original sourceWhere This Stands
Currently in committee. The next step in the legislative lifecycle is Floor Vote.
Procedural history
3 actions- Apr 14, 2025HouseRef To Com On Rules, Calendar, and Operations of the House
- Apr 14, 2025HousePassed 1st Reading
- Apr 10, 2025HouseIntroducedFiled
Version history
Only one version on file - nothing to compare yet. As later stages (committee substitute, engrossed, enrolled) are captured, the redline appears here.
View official text →Lobbying Activity
No state lobbying filings in our records match this bill. Federal lobbying reports (LDA) cover Congress, so they are not listed on state bills.
Full breakdown
Who this bill affects and the strongest case for and against it, written only from the bill’s own text.
Sponsors
Discoveries
Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.
Direct Cost Allocation for Tech Infrastructure
The legislation shifts financial responsibility for major grid upgrades directly onto commercial data centers rather than bundling them into general ratepayer charges.
Connected Entities
Sources
www.ncleg.gov
Analysis Score
0–100- Significance80How much this matters to a regular citizen
- Controversy65Intensity of disagreement among stakeholders
- Entertainment10Compellingness for a non-policy-wonk reader
- Buzz70Current news / social attention level