NewsABC7 WWSBOctober 27, 2026Manatee County

Venice City Council adopts 12-month moratorium on large-scale data center applications

Photo: ABC7 WWSB

The Venice City Council adopted a 12-month moratorium on Oct. 27 that immediately pauses the city's acceptance, review, processing, and approval of development applications and permits for large-scale data centers and facilities with major utility demands. The pause covers comprehensive plan amendments, rezonings, land development regulation changes, conditional uses, design alternatives, site and development plans, and building permits.

Read the full story at ABC7 WWSB

Why It Matters

The ordinance halts the permitting and review process for any facility with a monthly peak electrical load of 50 megawatts or more while city staff study local impacts on water supply, electrical capacity, and the environment.

Key Facts

  • The Venice City Council adopted a 12-month moratorium on development applications and permits for large-scale data centers on Oct. 27.
  • The pause immediately halts the city's acceptance, review, processing, and approval of applications connected to construction, expansion, or operation of covered facilities.
  • A large-scale data center is defined under the ordinance as a single location with an anticipated monthly peak electrical load of 50 megawatts or more.
  • The paused application types include comprehensive plan amendments, rezonings, land development regulation changes, conditional uses, design alternatives, site and development plans, and building permits.
  • City staff will use the moratorium period to review potential impacts on water supply, wastewater treatment, electrical capacity, and land-use compatibility.
  • The review will also consider environmental concerns such as potential effects on wetlands, coastal ecosystems, noise, lighting, and nearby land uses.
  • The moratorium will remain in effect for 12 months unless the city adopts related changes to its comprehensive plan, land development regulations, or code sooner.
  • The city council may extend the moratorium through another ordinance following public hearings.
  • A city business impact estimate states there are no large-load-customer businesses currently in Venice and none that have indicated plans to enter the city.

Who's Mentioned