NewsFox 13 News (WTVT) — All NewsNovember 11, 2026Hillsborough County
Auburndale residents and leaders challenge developers over proposed hyperscale data center's power and water…
Photo: Fox 13 News (WTVT) — All News
Hundreds of Auburndale residents and local leaders attended a public workshop to question developers about the massive power, water, and noise impacts of a proposed hyperscale data center along Pace Road. The project, purchased by Pace Road DC Development LLC in December 2025, requires city building permit and site plan reviews before proceeding. State law requires data centers to cover their own electrical infrastructure costs, though utility tariff approvals are still pending.
Read the full story at Fox 13 News (WTVT) — All NewsWhy It Matters
The proposed facility would consume up to 700 megawatts of electricity—equivalent to the power used by 500,000 homes—raising local concerns about resource strain, noise, and property values while promising 292 permanent jobs.
Key Facts
- Hundreds of Auburndale residents and local leaders packed a public workshop to challenge developers over a proposed hyperscale data center.
- The proposed data center would occupy a 75-acre site along Pace Road.
- The property was purchased in December 2025 by Pace Road DC Development LLC.
- Auburndale city commissioners previously approved a land-use designation and rezoning for the property in December 2023, with construction on the first two buildings beginning in early 2024.
- Electricity demand for the facility is projected to start at 350 megawatts and eventually reach 700 megawatts, enough to power up to 500,000 homes.
- TECO is slated to supply power to the facility, pending approval of a new tariff from the Florida Public Service Commission.
- Florida Senate Bill 484 requires data centers to cover their own electricity and infrastructure costs rather than passing them to other ratepayers.
- The facility is estimated to use more than 4,600 gallons of potable water per day, and developers plan to use a closed-loop cooling system.
- Developers project the facility will create 292 permanent jobs and will not receive financial incentives.
- The developer plans to limit noise at the property line to 50 decibels, equivalent to a quiet office.
- The first two buildings are expected to become operational by 2029.
- The developer submitted a building permit application and interior retrofit site plan on November 4, which still require city review.
Who's Mentioned
locationPace Road“Location of the 75-acre site for the proposed data center.”PersonTeresa Detweiler“Local resident who expressed concerns regarding property values.”OrganizationFlorida High Tech Corridor“An innovation district established about 30 years ago that includes the project.”locationAuburndale“City where the proposed data center is located and where residents held a public”PersonSean Levy“Auburndale City Commissioner who expressed concerns about protecting local resou”OrganizationFlorida Public Service Commission“State agency that needs to approve TECO's new tariff governing data center costs”OrganizationPace Road DC Development LLC“The company behind the current data center proposal that purchased the property ”OrganizationTECO“The utility provider slated to supply electricity to the data center.”