NewsABC Action News (WFTS) — NewsNovember 17, 2026Hillsborough County

Auburndale drafts a one-year data center moratorium while exempting a controversial Pace Road project

Photo: ABC Action News (WFTS) — News

Auburndale city staff is drafting a one-year moratorium on future data center projects, but the proposed pause will not halt a controversial data center planned by Hillwood Development Company along Pace Road. The city expects the moratorium proposal to reach commissioners for a first reading in December and a final vote in January, while continuing to negotiate a separate development agreement with Hillwood for a vote in early 2027.

Read the full story at ABC Action News (WFTS) — News

Why It Matters

Residents near the proposed Pace Road data center face potential changes to local electricity demand, water use, and neighborhood activity as the city weighs permitting and a binding development agreement, despite public opposition and a planned citywide on future projects.

Key Facts

  • Auburndale city staff is drafting a one-year moratorium on future data center projects to establish better standards.
  • The proposed moratorium would exempt the Hillwood Development Company project along Pace Road because the property is already zoned to allow a data center.
  • The city commission expects to review the moratorium proposal for a first reading in December and a possible final vote in January.
  • The Pace Road project involves converting two existing warehouse buildings into a data center near Florida Polytechnic University.
  • A text-message survey of 13,057 registered Auburndale voters by James Fishback's staff received 1,445 valid responses, with 86.7% opposing the data center.
  • The property was annexed in December 2022 and rezoned as an Industrial Planned Unit Development in December 2023, allowing research, light manufacturing, and information sciences.
  • Hillwood submitted an application on November 4 for the interior retrofit of the two warehouse buildings.
  • Hillwood estimates the facility will use approximately 4,665 gallons of water per day using a closed-loop cooling system.
  • Hillwood projects the full buildout of the data center could require up to 700 megawatts of electricity, supplied by Tampa Electric Company.
  • The developer projects approximately 300 permanent jobs and up to 1,300 construction jobs at peak activity.
  • Auburndale is negotiating a separate development agreement with Hillwood that is expected to come before the commission for a vote in the first quarter of 2027.