Construction Contract for O'Hare Runway 9C-27C

Original title: Contract 24641: WALSH/T J LAMBRECHT JV — CONSTRUCTION-AVIATION (Chicago, IL)

Record date · May 4, 2012

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

What This Bill Does

This document outlines a $270,011.40 construction contract awarded to the joint venture WALSH/T J LAMBRECHT for work on the O'Hare Modernization Project. The project specifically covers the Northeast package for .

Why it matters

This contract allocates $270,011.40 in public funds toward the ongoing expansion and modernization of O'Hare International Airport's runway infrastructure.

Who It Affects

Groups the bill's text affects, as described in the record. Being affected is not a position for or against it.

Directly affected

WALSH/T J LAMBRECHT JV

The entity is responsible for performing the construction work defined in the contract.

Directly affected

O'Hare Modernization Project

The department is responsible for managing the execution of the runway construction project.

Key Facts

  • The contract was awarded to WALSH/T J LAMBRECHT JV.
  • The total contract award amount is $270,011.40.
  • The contract is designated for the O'Hare Modernization Project.
  • The specific scope of work is the Runway 9C-27C Northeast Package.
Show all 6 facts
  • The contract was approved on May 4, 2012.
  • The vendor is located at 929 W Adams St, Chicago, IL, 60607.

Frequently Asked Questions

What is this contract for?
It is for construction services related to the Northeast package of at O'Hare International Airport.
How much is the contract worth?
The total award amount is $270,011.40.
When was this contract approved?
The contract was approved on May 4, 2012.

What else do you want to know?

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Full breakdown

Who this bill affects and the strongest case for and against it, written only from the bill’s own text.

Connected Entities

OHARE MODERNIZATION PROJECT, WALSH/T J LAMBRECHT JV, Chicago, IL
OrganizationOHARE MODERNIZATION PROJECT“The department overseeing the runway construction.”Map →
OrganizationWALSH/T J LAMBRECHT JV“The vendor awarded the construction contract.”Map →
locationChicago, IL“The jurisdiction and location of the project.”Map →

Sources

Open source document

data.cityofchicago.org

Analysis Score

0–100
  • Significance40
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz5
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record