The 30-second read
Recorded outcomeThe Greensboro City Council voted 8-1 to authorize a contract for the first phase of construction on the Steven B. Tanger Performing Arts Center. The agreement sets a maximum cost of $2,501,729.15 and allows city staff to pursue alternative construction options if this price cannot be finalized with the selected contractor.
Why it matters
This decision commits over $2.5 million in city funds to begin the first phase of construction for the Tanger Performing Arts Center, a project involving a total estimated cost of $78.1 million shared between the city and the Community Foundation of Greater Greensboro.
What happens next
No later meeting or follow-up date is stated in the reviewed record.