Approval of $1.28 Million Cost Increase for New Police Headquarters Construction

Original title: Motion Approving Change Order No. 24 for Construction Management at Risk Services for New Police Headquarters - Moss & Associates, LLC - $1,284,060.50 - (Commission Districts 1, 2, 3 and 4)

Record date · May 6, 2025

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

Public stanceCommunity reactions are separate from the official record and reporting.

What This Bill Does

The local government has approved a $1,284,060.50 increase to the construction management contract for the new police headquarters. This , designated as number 24, involves the firm Moss & Associates, LLC.

Why it matters

This action increases the total taxpayer-funded budget for the new police headquarters by over $1.28 million, affecting the project's overall cost and completion timeline for residents in Commission Districts 1, 2, 3, and 4.

Who It Affects

Groups the bill's text affects, as described in the record. Being affected is not a position for or against it.

Directly affected

Moss & Associates, LLC

The firm receives an additional $1,284,060.50 for construction management services.

Directly affected

Residents of Commission Districts 1, 2, 3, and 4

These residents are the primary service area for the new police headquarters and are impacted by the project's budget and construction status.

Key Facts

  • The government approved Change Order No. 24 for the new police headquarters project.
  • The approved cost increase is $1,284,060.50.
  • The contract is held by Moss & Associates, LLC for Construction Management at Risk services.
  • The project impacts Commission Districts 1, 2, 3, and 4.
Show all 6 facts
  • The motion was passed by the Finance body.
  • The motion was introduced on March 5, 2025.

Frequently Asked Questions

What is a 'Change Order'?
A is a formal document used to modify the terms of an existing construction contract, often resulting in changes to the project's cost or scope.
What does 'Construction Management at Risk' mean?
It is a project delivery method where the construction manager provides professional services and acts as a consultant to the owner during the design and construction phases, while also taking on the risk of completing the project at a guaranteed maximum price.

What else do you want to know?

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Full breakdown

Who this bill affects and the strongest case for and against it, written only from the bill’s own text.

Discoveries

1 pattern noticed across the record

Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.

financial connection90% confidence

High Frequency of Change Orders

The document is labeled 'Change Order No. 24', suggesting a high volume of modifications to the original construction contract.

Sources

Open source document

webapi.legistar.com

Analysis Score

0–100
  • Significance65
    How much this matters to a regular citizen
  • Controversy20
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz15
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record