Read. Follow. Verify.Approval of Additional Costs and Time for Margate Boulevard Improvement Project
Record date · March 11, 2026
Track this bill to get notified when it advances a stage. One tap to stop, anytime.
What This Bill Does
The Community Redevelopment Agency is approving two final s for the Margate Boulevard crosswalk and landscape project. These changes increase the total project cost by $1,457.37 and extend the construction timeline by two days.
This resolution authorizes a total payment increase of $1,457.37 to FG Construction, LLC and extends the project completion deadline by two days, impacting the final budget and schedule for the Margate Boulevard improvements.
Who It Affects
Groups the bill's text affects, as described in the record. Being affected is not a position for or against it.
FG Construction, LLC
The company receives an additional $1,457.37 in payment and is granted two extra days to complete the project.
Community Redevelopment Agency
The agency is authorizing the expenditure of additional funds and extending the project timeline.
Key Facts
- Change Order No. 6 adds $467.97 to the project cost.
- Change Order No. 7 adds $989.40 to the project cost.
- The total combined cost increase for the project is $1,457.37.
- The project contract time is extended by 2 additional days.
Show all 6 facts
- The Board Chair is authorized to sign the change orders on behalf of the agency.
- The project is officially titled the Margate Boulevard Crosswalk and Landscape Improvements Project.
Frequently Asked Questions
How much extra will this project cost?
Will the construction take longer?
What else do you want to know?
News Coverage
Follow the record
Votes, people, money & the original sourceFull breakdown
Who this bill affects and the strongest case for and against it, written only from the bill’s own text.
Discoveries
Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.
Incremental Project Costing
The project is utilizing multiple small change orders (6 and 7) to finalize costs, suggesting a standard close-out process for the construction agreement.
Connected Entities
Sources
webapi.legistar.com
Analysis Score
0–100- Significance20How much this matters to a regular citizen
- Controversy5Intensity of disagreement among stakeholders
- Entertainment5Compellingness for a non-policy-wonk reader
- Buzz10Current news / social attention level
Publisher tools