Approval of Final Payment and Project Changes for Oslo Road and 90th Avenue Improvements

Original title: Release of Retainage and Approval of Change Order No. 1 Oslo Road and 90th Avenue Roadway Improvements (IRC-2215)

July 15, 2025

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

The Frame

What this does

This decision authorizes the final payment of withheld funds to the contractor and approves modifications to the project scope or costs for the Oslo Road and 90th Avenue intersection improvements.

Who is mentioned in the record

Potentially affected actors named in the source documents. Mention is not a position.

Construction Contractor

The contractor receives the released retainage funds and is subject to the terms of the approved change order.

Local Residents

Residents in the vicinity of Oslo Road and 90th Avenue are affected by the completion and final adjustments of the roadway improvement project.

What changed

Last recorded activity July 15, 2025.

What's next

Next step not available in the current record.

Summary

The Board of County Commissioners approved the release of withheld funds () and a formal for the road improvement project at Oslo Road and 90th Avenue (IRC-2215). This action finalizes the financial and contractual adjustments for the construction project.

Key Facts

  • The Board of County Commissioners approved the release of retainage for the Oslo Road and 90th Avenue project.
  • The Board approved Change Order No. 1 for the project.
  • The project is identified by the code IRC-2215.
  • The action was processed as a Consent Staff Report.
  • The document was introduced and passed on June 25, 2025.

Why It Matters

This decision authorizes the final payment of withheld funds to the contractor and approves modifications to the project scope or costs for the Oslo Road and 90th Avenue intersection improvements.

Frequently Asked Questions

What is 'retainage'?
is a portion of the contract price withheld from a contractor until the project is completed to ensure all work is finished according to specifications.
What does a 'change order' mean?
A is a formal document that modifies the original contract, often adjusting the scope of work, project timeline, or total cost.

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Connected Entities

otherIRC-2215The project identification number.Map →
other25-0700The file number for the staff report.Map →
locationOslo Road and 90th Avenue Roadway ImprovementsThe specific infrastructure project site.Map →
organizationBoard of County CommissionersThe governing body that approved the release of funds and the change order.Map →

Sources

Open source document

webapi.legistar.com

Analysis Score

0–100
  • Significance40
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz10
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record