Contract for O'Hare South Airfield Site Preparation

Original title: Contract 26117: TURNER-CONCRETE STRUCTURES-LINDAHL TRI VENTURE — CONSTRUCTION-AVIATION (Chicago, IL)

Record date · April 18, 2013

Track this contract to keep it in your saved records and follow what happens to it. One tap to stop, anytime.

What This Contract Does

This document outlines a construction contract awarded to the Turner-Concrete Structures-Lindahl for site preparation work on at O'Hare International Airport. The contract, valued at a negative adjustment of $172,554.50, was approved on April 18, 2013.

Why it matters

This contract adjustment impacts the budget and scope of the O'Hare Modernization Project, specifically affecting the site preparation phase for the South Airfield runway.

Who It Affects

Groups the contract's text affects, as described in the record. Being affected is not a position for or against it.

Directly affected

TURNER-CONCRETE STRUCTURES-LINDAHL TRI VENTURE

The vendor is responsible for the site preparation work and is subject to the financial terms of the contract.

Directly affected

O'Hare Modernization Project

The department is managing the construction project and the associated budget adjustments.

Key Facts

  • The contract is identified as number 26117.
  • The project involves site preparation for the South Airfield Runway 10R-28L at O'Hare.
  • The contract award amount is a negative adjustment of $172,554.50.
  • The contract was officially approved on April 18, 2013.
Show all 5 facts
  • The work is categorized under construction-aviation services.

Frequently Asked Questions

What is the purpose of this contract?
The contract is for site preparation work related to the South Airfield at O'Hare International Airport.
Why is the contract amount negative?
The document lists the amount as $-172,554.5, indicating a credit or a reduction in the total contract value.

What else do you want to know?

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Full breakdown

Who this contract affects and the strongest case for and against it, written only from the contract’s own text.

Discoveries

1 pattern noticed across the record

Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.

financial connection90% confidence

Negative Contract Adjustment

The contract value is listed as a negative amount, suggesting a budget reduction or credit rather than a new expenditure.

Connected Entities

TURNER-CONCRETE STRUCTURES-LINDAHL TRI VENTURE, OHARE MODERNIZATION PROJECT, 55 E MONROE ST, CHICAGO, IL, 60603

Sources

Open source document

data.cityofchicago.org

Analysis Score

0–100
  • Significance40
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz5
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record