What this does

The contract authorizes the expenditure of $6,040,842 in public funds for specific airport infrastructure grading work to be completed by Kiewit-Reyes, .

Who is mentioned in the record

Potentially affected actors named in the source documents. Mention is not a position.

Kiewit-Reyes, AJV

The vendor is obligated to perform the specified mass grading construction work in exchange for the contract payment.

O'Hare Modernization Project

The department is responsible for managing the project and overseeing the expenditure of the $6,040,842.

What changed

Last recorded activity January 6, 2009.

What's next

Next step not available in the current record.

Key Facts

  • The contract award amount is $6,040,842.
  • The vendor is Kiewit-Reyes, AJV.
  • The contract was approved on January 6, 2009.
  • The project is identified as 10C - 28C Mass Grading (East) South.
  • The project specification number is 47123.
  • The work is categorized under Construction-Aviation.
  • The project is managed by the O'Hare Modernization Project department.
  • The vendor is located at 2230 Point Blvd Ste 100, Elgin, IL, 60123.

Why It Matters

The contract authorizes the expenditure of $6,040,842 in public funds for specific airport infrastructure grading work to be completed by Kiewit-Reyes, .

Frequently Asked Questions

What is the purpose of this contract?
The contract is for work (10C-28C East South) at O'Hare International Airport.
How much is the city paying for this work?
The total award amount for this contract is $6,040,842.

Summary

This document details a $6,040,842 construction contract awarded to Kiewit-Reyes, for work at O'Hare International Airport. The project is part of the O'Hare Modernization Program, specifically designated as the 10C-28C Mass Grading (East) South project.

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Connected Entities

Sources

Open source document

data.cityofchicago.org

Analysis Score

0–100
  • Significance40
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz5
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record