What this does

The contract adjustment reduces the total project cost for the Wacker Drive reconstruction by $318,880, affecting the budget managed by the Chicago Department of Transportation.

Who is mentioned in the record

Potentially affected actors named in the source documents. Mention is not a position.

James P. McHugh Construction Co.

The company's contract value is reduced by $318,880.

Chicago Department of Transportation

The department is responsible for the oversight and budget management of the Wacker Drive viaduct reconstruction.

What changed

Last recorded activity July 3, 2012.

What's next

Next step not available in the current record.

Summary

This document records a financial adjustment of -$318,880 to an existing construction contract held by James P. McHugh Construction Co. for the Wacker Drive project between Randolph and Monroe Streets.

Key Facts

  • The contract for the Wacker Drive viaduct reconstruction (Randolph Street to Monroe Street) was adjusted by -$318,880.
  • The contract is identified as number 23813.
  • The project is managed by the Chicago Department of Transportation.
  • The vendor for the project is James P. McHugh Construction Co.
  • The adjustment was officially approved on July 3, 2012.
  • The vendor is located at 1737 S Michigan Avenue, Chicago, IL.

Why It Matters

The contract adjustment reduces the total project cost for the Wacker Drive reconstruction by $318,880, affecting the budget managed by the Chicago Department of Transportation.

Frequently Asked Questions

What is the purpose of this contract adjustment?
The document records a financial change of -$318,880 to the Wacker Drive reconstruction project.
Who is the contractor for the Wacker Drive project?
James P. McHugh Construction Co. is the vendor listed for this contract.

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Discoveries

Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.

financial connection90% confidence

Contract Value Reduction

The document represents a negative adjustment to a large-scale construction contract, indicating a reduction in project scope or cost.

Connected Entities

Sources

Open source document

data.cityofchicago.org

Analysis Score

0–100
  • Significance40
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz5
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record