NASA Funding Extension for NuSTAR Space Mission
Track this bill to get notified when it advances a stage. One tap to stop, anytime.
The Frame
This contract provides $139.39 million in federal funding to the California Institute of Technology to advance the design and development of the NuSTAR space telescope mission through June 2008.
Potentially affected actors named in the source documents. Mention is not a position.
California Institute of Technology
The institution is responsible for managing the NuSTAR mission tasks and meeting specific engineering and procurement milestones.
NASA
The agency is providing funding and oversight for the development of the NuSTAR mission.
No recent stage movement in the current record.
Next step not available in the current record.
Summary
Key Facts
- NASA awarded $139.39 million to the California Institute of Technology for the NuSTAR mission.
- The contract extension covers the period from March 1, 2008, to June 30, 2008.
- The contractor must manage NuSTAR tasks and provide cost and schedule reporting to NASA.
- The contractor is required to work with JPL to finalize project requirements for the System Requirements Review (SSR).
- The contractor must design the focal plane assembly, instrument enclosures, shield, and aperture.
- The contractor is authorized to identify and initiate procurement of long-lead parts and items.
- The contractor must complete the glass production facility and verify production capability for NuSTAR glasses.
- The contractor must develop prototypes and designs for the optics assembly.
- The contractor must complete the preliminary design of the mast, canister, and instrument structure.
- The contractor must complete spacecraft requirements and continue baseline spacecraft design.
- The contractor must complete the Mission Operations System (MOS) requirements and preliminary plan.
Frequently Asked Questions
What is the NuSTAR mission?
What is the purpose of this specific funding?
Why It Matters
This contract provides $139.39 million in federal funding to the California Institute of Technology to advance the design and development of the NuSTAR space telescope mission through June 2008.
News Coverage
Discoveries
Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.
Short-term Bridge Funding
The contract is a short-term four-month extension, indicating a bridge period to maintain project continuity.
Connected Entities
Sources
www.usaspending.gov
Analysis Score
0–100- Significance60How much this matters to a regular citizen
- Controversy10Intensity of disagreement among stakeholders
- Entertainment5Compellingness for a non-policy-wonk reader
- Buzz10Current news / social attention level