What This Bill Proposed
The Commissioner of Energy and Environmental Protection must convene a working group by October 1, 2026, to study electric transmission facility siting and grid capacity planning, with a report due to the General Assembly by July 1, 2027.
Establishes a formal state study group tasked with examining infrastructure bottlenecks, distributed energy integration, and cost-sharing rules for future power developers, potentially shaping future electric utility regulations and project expenses.
Who It Would Have Affected
Groups the bill's text would have affected, as described in the record. Being affected is not a position for or against it.
electric distribution companies
Must provide representatives to participate in the DEEP working group examining grid capacity and transmission siting.
distributed generation developers
Subject to future recommendations regarding cost-sharing and cost-shifting mechanisms for infrastructure improvements.
Key Facts
- The Commissioner of Energy and Environmental Protection must convene a working group within DEEP by October 1, 2026.
- The working group must study electric transmission facility siting and long-term electric grid interconnection and capacity planning.
- The group is charged with examining administrative or interagency delays in siting transmission facilities.
- The group must evaluate needs for grid enhancements, including additional interconnection points for distributed generation sources.
Show all 8 facts
- The group must review potential cost-sharing or cost-shifting mechanisms to prevent distributed generation developers from bearing inequitable infrastructure costs.
- Required members of the working group include the DEEP commissioner, PURA chairperson, Consumer Counsel, OPM secretary, DAS commissioner, and representatives of electric distribution companies.
- The commissioner must submit a report detailing the working group's findings and legislative recommendations to the energy and technology committee by July 1, 2027.
- The fiscal impact statement projects no state or municipal cost resulting from the bill.
Frequently Asked Questions
Who serves on the new working group?
When is the working group required to report its findings?
What else do you want to know?
News Coverage
Follow the record
Votes, people, money & the original sourceWhere This Stands
This bill did not become law - Died at adjournment · on the Senate floor.
Procedural history
9 actions- Mar 31, 2026Connecticut General AssemblyFile Number 276
- Mar 31, 2026SenateSenate Calendar Number 187
- Mar 31, 2026SenateFavorable Report, Tabled for the Calendar, Senate
- Mar 31, 2026Connecticut General AssemblyReported Out of Legislative Commissioners' Office
- Mar 25, 2026Connecticut General AssemblyReferred to Office of Legislative Research and Office of Fiscal Analysis 03/30/26 5:00 PM
- Mar 18, 2026Connecticut General AssemblyFiled with Legislative Commissioners' Office
Show 3 earlier actions
- Mar 17, 2026Connecticut General AssemblyJoint Favorable
- Feb 27, 2026Connecticut General AssemblyPublic Hearing 03/05
- Feb 26, 2026Connecticut General AssemblyCommitteeReferred to Joint Committee on Energy and Technology
Version history
Only one version on file - nothing to compare yet. As later stages (committee substitute, engrossed, enrolled) are captured, the redline appears here.
View official text →Lobbying Activity
No state lobbying filings in our records match this bill. Federal lobbying reports (LDA) cover Congress, so they are not listed on state bills.
Full breakdown
Who this bill affects and the strongest case for and against it, written only from the bill’s own text.
Sponsors
Connected Entities
Sources
cga.ct.gov
Analysis Score
0–100- Significance20Lowered because this bill did not pass (its text scored 45)
- Controversy10Intensity of disagreement among stakeholders
- Entertainment5Compellingness for a non-policy-wonk reader
- Buzz20Current news / social attention level
Publisher tools