Passed

Approval of $22.7 Million Contract for New Fire and EMS Stations

Original title: Motion Approving Agreement Pursuant to a Multi-Step Procurement Process, Request for Qualifications (RFQ) No. 522-2, Pre-Qualification for Design-Build Services (Step 1); and Request for Proposals (RFP) No. 558-3 for Design-Build Services (Step 2) for Fire Station No. 13 and Emergency Medical Sub-Station No. 88 - CORE Construction Services of Florida, LLC - $22,745,045 (no alternates) - (Commission Districts 2 and 4)

Record date · May 5, 2026

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

Public stanceCommunity reactions are separate from the official record and reporting.

What This Bill Does

The local government has approved a $22,745,045 contract with CORE Construction Services of Florida, LLC to design and build Fire Station No. 13 and Emergency Medical Sub-Station No. 88. This decision follows a two-step competitive bidding process involving pre-qualification and proposal submission.

Why it matters

Residents in Commission Districts 2 and 4 will receive new emergency response infrastructure funded by a $22.7 million capital expenditure.

Who It Affects

Groups the bill's text affects, as described in the record. Being affected is not a position for or against it.

Directly affected

Residents of Commission Districts 2 and 4

These residents will have new fire and emergency medical facilities constructed in their districts.

Directly affected

CORE Construction Services of Florida, LLC

The company is contracted to perform the design and construction work for the specified amount.

Key Facts

  • The government approved a $22,745,045 contract for the construction of Fire Station No. 13 and Emergency Medical Sub-Station No. 88.
  • The project was awarded to CORE Construction Services of Florida, LLC.
  • The selection process involved a two-step procurement: RFQ No. 522-2 (Pre-Qualification) and RFP No. 558-3 (Proposal).
  • The contract includes no alternate project options.
Show all 6 facts
  • The facilities will serve Commission Districts 2 and 4.
  • The motion (File 26-0386) has officially passed.

Frequently Asked Questions

Where will the new stations be located?
The stations are designated for Commission Districts 2 and 4.
How was the construction company chosen?
The company was selected through a two-step procurement process consisting of a Request for Qualifications (RFQ) and a Request for Proposals (RFP).

What else do you want to know?

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Full breakdown

Who this bill affects and the strongest case for and against it, written only from the bill’s own text.

Sources

Open source document

webapi.legistar.com

Analysis Score

0–100
  • Significance65
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz20
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record