Citywide Sidewalk Replacement Contract Approval

Original title: A resolution approving a proposed Contract between the City and County of Denver and Keene Concrete, Inc. to remove existing deficient sidewalk throughout the city and replace to ADA and City standards. Approves a contract with KEENE CONCRETE, INC. for $3,424,371.00 with a term of NTP + 220 Days to remove existing deficient sidewalk throughout the city and replace to ADA and City standards, citywide (DOTI-202683590). The last regularly scheduled Council meeting within the 30-day review period is on 6-29-2026. The Committee approved filing this item at its meeting on 6-3-2026.

Record date · June 15, 2026

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

Public stanceCommunity reactions are separate from the official record and reporting.

What This Bill Does

The City and County of Denver has approved a $3.4 million contract with Keene Concrete, Inc. to remove and replace damaged sidewalks across the city to meet and municipal standards.

Why it matters

Residents across Denver will see construction activity to replace deficient sidewalks over the next 220 days following the Notice to Proceed, funded by a $3,424,371 city contract.

Who It Affects

Groups the bill's text affects, as described in the record. Being affected is not a position for or against it.

Directly affected

Keene Concrete, Inc.

The company is contracted to perform the sidewalk removal and replacement work for the city.

Directly affected

Denver residents

Residents will experience construction activity and sidewalk access changes during the 220-day project period.

Key Facts

  • The City and County of Denver approved a contract with Keene Concrete, Inc. for $3,424,371.00.
  • The project involves removing and replacing deficient sidewalks citywide.
  • All new sidewalk work must meet ADA (Americans with Disabilities Act) and City standards.
  • The contract duration is set for 220 days following the Notice to Proceed (NTP).
Show all 8 facts
  • The project is tracked under internal reference number DOTI-202683590.
  • The Committee approved filing this item on 6-3-2026.
  • The resolution was introduced on 5-22-2026 and has been adopted.
  • The final council meeting within the 30-day review period was 6-29-2026.

Frequently Asked Questions

Will my sidewalk be replaced?
The contract covers 'deficient' sidewalks citywide, but the document does not list specific addresses or neighborhoods.
How long will the construction take?
The contract term is 220 days starting from the Notice to Proceed date.

What else do you want to know?

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Full breakdown

Who this bill affects and the strongest case for and against it, written only from the bill’s own text.

Discoveries

1 pattern noticed across the record

Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.

policy shift90% confidence

ADA Compliance Focus

The contract explicitly ties sidewalk replacement to ADA standards, indicating a prioritized effort to bring city infrastructure into federal compliance.

Sources

Open source document

denver.legistar.com

Analysis Score

0–100
  • Significance45
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz15
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record